Repave, Resurface, or Overlay the Existing Asphalt Parking Lot
We supply all labor, materials, and equipment needed to repave the existing “Asphalt Parking Lot”.
Step 1: CUT PAVEMENT BACK AT SEAMS
This includes removing one to two feet of pavement at all seams. We do this in order to match back smoothly to the existing joints and create a butt joint for a perfect fit.
Step 2: ADJUST DRAIN AND MANHOLE COVERS
Adjust drain & manhole covers to new grade elevations
Step 3: ADJUST LOW AREAS AND HIGH AREAS
Raise low areas and lower high areas. Fill cracks over 1/8th inch wide by cleaning and filling with hot rubberized crack material.
Step 4:ASPHALT INSTALLATION
A new wearing course is installed with hot Asphalt, to comply with New York State Mix to specifications and placed at an average temperature of 300°F . This new surface is installed by a mechanical self powered paver machine.
Step 5:ASPHALT COMPACTION
The new asphalt pavement is then compacted by a vibratory power roller.
Step 6: JOIN OLD AND NEW PAVEMENT
Apply hot liquid Asphalt Concrete (A.C.) “Tar” along seam to join old and new pavement.